Quality and inspection

Quality Control in Metal Fabrication: What Gets Checked at Each Step

Grinding a weldment on a fixture table at HPS Fabrications, sparks coming off the grinder

Quality control in metal fabrication works as a check at every step, not one inspection at the end. At HPS Fabrications, incoming material is inspected, every piece is cut from a checked cut list, and each part is checked by the fabricator who built it and then by our quality control manager before it moves on. A defect caught at its own step takes one fix; caught at the end, it takes undoing every step built on top of it.

Where quality is checked in our shop, and by whom
Who checksWhat gets checked
Incoming materialQuality controlEvery delivery, before it goes into production
CuttingThe saw operatorEach piece cut to the cut list and checked off as it is cut
Fit upThe fabricator, then quality controlThe fit of the part, against the in-process quality sheet
WeldingQuality controlSpatter, over-grinding, undercut, underfill, porosity, cracks and weld size
DimensionsQuality control, from the print at the stationOverall sizes and the quantities the job calls for
Finish and hardwareQuality controlMaterial finish and torque specifications
ReleaseQuality controlA green tag to move on, a red tag to stop

Quality control is a check at every step, made first by the person who did the work and then by quality control, before the part moves on. The table above is how that runs on our floor. Here is why the timing matters, and what an inspector looks at.

A defect costs whatever has been built on top of it

The defect is the same size wherever it is found. What changes is how much work sits on top of it. Picture one bracket on a structural steel maintenance platform, cut short at the saw:

  • Caught at the saw, against the cut list: one piece is cut again.
  • Caught at fit up, before any welding: one piece is cut again and refit.
  • Caught at final inspection: the welds are ground out and the piece replaced, then rewelded, refinished and inspected again.
  • Caught at installation: a repair in the field, with the plant’s crew waiting.

Every check below moves that discovery back toward the saw.

Every part is checked twice, then tagged green or red

Each fabricator fills in an in-process quality sheet for every job. The fabricator checks the part against that sheet first, and only then calls quality control to inspect it before the next step. A part that passes every point gets a green tag and moves on. A part that fails gets a red tag, and it does not.

Our quality control manager sees everything, from incoming material to outgoing: “everything has to come through me first.”

Material and cuts are checked before anything is welded

All incoming material is inspected before it goes into production. At the saw, every piece is cut to the length on a written cut list and checked off as it is cut.

Parts are fit up on fixture tables we build ourselves, with bolt-on stops that hold each part in the same place every time. That matters most on production runs, where the last part has to match the first. Higher-volume work runs at our Madison Heights facility, which has robotic welding.

What an inspector looks for on a weld

In plain English:

  • Spatter: beads of metal thrown off during welding that stick to the part.
  • Over-grinding: metal ground down so far that it is dished in.
  • Undercut: a groove melted into the part along the edge of the weld and left unfilled.
  • Underfill: a weld that does not fill the joint, so its face sits below the surface.
  • Porosity: gas trapped in the weld, showing as pinholes.
  • Cracks: in the weld or in the metal beside it.
  • Weld size: neither smaller nor larger than the drawing calls for.

The inspector also checks that the welder held the parameters, the settings the job calls for.

Dimensions, finish and torque are checked against the print

The prints hang at the fabricator’s station, and the inspector checks against the same drawings: overall sizes and quantities, then material finish, torque specifications and anything else critical to the job, before a part moves on to finishing and coating. Some assemblies are tested once they are put together: chain assemblies, for example, are pull tested.

The checks are only as good as the people doing the work

Inspection finds defects; skilled people prevent them. Our welders and fabricators are certified across carbon steel, stainless and aluminum, and retested on a regular schedule, and they read prints, not only run a bead.

Tom, a Six Sigma Black Belt from the automotive world, puts it this way: “we just look at everything from a quality standpoint and how we can deliver something that is not going to have quality concerns.” None of this makes a shop infallible. It makes a mistake smaller and cheaper when it happens. What we can substantiate in writing is on our quality and compliance page.

Put the same questions to us

The checklist below works on any shop, including ours. The rest of what to ask is in how to choose a metal fabricator. Request a quote with your drawing package, or describe what the part has to do, and tell us what it has to pass.

What to ask any fabricator about quality control

  • Who inspects the part? Someone other than the person who built it should check it before it moves on.
  • When does inspection happen? At each step, or only once the part is finished and the defects are buried.
  • What is it checked against? A cut list, an in-process sheet and the print, not memory.
  • What happens when a part fails? It should stop at the step where it failed, not travel on with a note.
  • Who confirms your requirements? Any code, test or record your contract names, confirmed in writing before the PO.

Common questions

Quality Control in Metal Fabrication: What Gets Checked at Each Step: questions buyers ask

What is the difference between in-process and final inspection?

In-process inspection happens before each part moves to the next step. Final inspection happens once the part is finished. A shop that only inspects at the end finds a defect after more work has been built on top of it. We do both: everything that leaves our shop has come through quality control.

What is the difference between quality assurance and quality control?

Quality assurance prevents defects: training, procedures and how the work is planned. Quality control finds them, by checking the actual parts. On our floor, retesting welders is assurance; the in-process sheets, inspections and tags are control.

Does checking at every step slow the job down?

It spreads the checking through the job instead of adding a block at the end. Our inspector checks parts as the work goes, so nothing waits on one large inspection before it ships, and a defect found early does not become rework late in the job.